If you have never had a fire alarm installed, it helps to know what the process involves and how it affects the people using the building.
1. Confirming the design on site
Before any cable goes in, the installer checks the design against the actual building. Walls move, ceilings are lower than the drawings show and tenants change layouts. Any differences are agreed with you and recorded.
2. Planning access and timing
Installation takes place in a building that people may be using. Access, working hours, noisy or dusty work and the order in which areas are completed are agreed in advance. Out-of-hours working is sometimes used for sensitive areas.
3. Containment and cabling
Cables are routed according to the design and fixed so that they are protected from damage. For non-domestic systems, BS 5839-1 has recommendations on cable type and installation, which the design takes into account. The electrical side of the installation is carried out to BS 7671.
4. Fitting devices and the control panel
Detectors, sounders and manual call points are installed and connected, along with the control panel and its power supply and standby batteries. If the system interfaces with other equipment, those connections are made and noted.
5. Completion checks
The installer checks that the work matches the design, records any variations and prepares as-installed drawings.
6. Handing over to commissioning
Installation is not the final step. The system must then be commissioned, which means programming and testing it. Only after that should it be handed over for use.
Typical disruption
- Short periods of access to ceilings and rooms
- Some noise and dust from drilling and cable fixing
- Ladders or platforms in circulation areas
- A planned changeover if an old system is replaced
To discuss an installation, see fire alarm installation.